Johnson Controls, Inc.

Automotive Interior Manufacturing Buildout.

Johnson Controls, a manufacturer of automotive interiors, selected Gray to provide design-build services for the original building and two subsequent additions on its Alabama campus.

In Numbers

  • Cottondale, AL
    Location
  • 381,000 s.f.
    Square Footage
  • Phase I: 6 months, Phase II: 8 months, Phase III: 11 months
    Operational
Johnson Controls, Inc.
Cottondale, AL
381,000 s.f.
Phase I: 6 months, Phase II: 8 months, Phase III: 11 months

This project was tackled in phases, with the original phase and building being completed in just five months. This project provided especially challenging conditions to Gray due to soft soil and heavily wooded areas.

Gallery

Explore Services

  • Specialty Equipment
    Custom equipment design-build Modular process skids
    OEM contract manufacturing Processing equipment
    Stainless-steel & specialty alloy fabrication Distributed products
  • Real Estate

    Incentive coordination

    Land acquisition

    Construction financing

    Build-to-suit/sale leaseback