Safety Luncheon Held at the Siemens Jobsite

In Numbers
- Charlotte, NCLocation
- 489,905 s.f.Square Footage
- 13 monthsOperational
The Siemens Energy, Inc. project in Charlotte, N.C. hosted a safety luncheon on Wednesday, April 6th, 2011. In the fall of 2010, Siemens selected Gray Construction to design and build its new 450,000 s.f. 60-Hz gas turbine production plant adjacent to its existing steam turbine plant. Gray hosts a safety luncheon on each jobsite to show appreciation to the many subcontractors and Gray team members who help put safety and quality of life first. Safety is a top priority at Gray. In fact, it’s our No. 1 Core Value. The Siemens safety luncheon celebrated the following:
-
- 165 days on site
-
- 90,102 man hours to date
-
- 0 days with zero lost time incidents
-
- 12 contractors on site
-
- 190 average daily manpower
-
- 430,000 cubic yards of dirt removed
-
- 33,788 tons of stone removed
-
- 5,000 cubic yards of concrete poured
-
- 3,500 tons of steel erected
If you have manufacturing plant construction needs, please contact Phil Seale, Vice President, Manufacturing at [email protected].
- Category:
- Corporate News
Some opinions expressed in this article may be those of a contributing author and not necessarily Gray.
Related News & Insights
Gray Celebrates Grand Opening of Wistron's First U.S. Advanced Manufacturing Facility
Corporate News
July 22, 2026Building The Next Generation
Stories
July 16, 2026Advanced Technology, Construction
Why Industrial Projects Should Align Design & Construction Early
Industry
July 08, 2026