Recovery Data Center
Automated Systems and Controls Enable Precise Cooling.
A customer in the Data Centers market selected Spencer Bristol Engineering, a Gray company, to provide MEP engineering and automated controls for its data center’s chillers, cooling systems, and storage tanks.
Spencer Bristol provided MEP design engineering for the installation of new HVAC, electrical, and control systems in a customer’s recovery data center. Project design included a modular chiller plant providing N+1 cooling to the data center floor, along with a traditional central chiller plant providing N+1 cooling to the backup recovery unit office areas. An innovative scheme of automated control valves allowed any chiller to provide cooling to all areas of the facility, resulting in redundancy greater than 2N.
Project services:
- Conceptual, schematic, design development, & contract documents
- Field engineering
- Contract administration
- Commissioning
To learn more about Spencer Bristol Engineering’s service capabilities, click here.