Back Menu

THAI SUMMIT AMERICA CORPORATION

Howell, Mich.
Add to Favorites Remove from Favorites

Thai Summit America Corporation, a major supplier of stamped parts for the automotive industry, selected Gray to expand 58,000 s.f. on its existing automotive stamping and assembly facility in Michigan. This expansion was built to supply door panels for one of Ford Motor Company’s flagship products, F-150 pickup trucks. Gray was later selected to complete a tandem and blanking line expansion, adding 55,574 s.f. to the facility. 

Project Facts

  • Total Area: 113,574 s.f.
    • Phase I – Assembly area: 52,000 s.f. and scrap building area: 6,000 s.f.
    • Phase II – Press pit
    • Phase III – Tandem line expansion: 55,574 s.f.
  • Schedule: 16 month schedule
    • Phase I – 16 months
    • Phase II – 3 months
    • Phase III – 8 months
  • Building features:
    • Pre-engineered metal building
    • Concrete walls
  • Notable building istallations:
    • (8) dock levelers
    • (3) press pits
    • Scrap conveyor tunnels and system
    • Tandem pit

Services Provided by Gray:

  • Financial Services/Leaseback
  • Architecture
  • Civil Engineering
  • MEP Engineering
  • Structural Engineering
  • Construction Management
  • Equipment Procurement
  • Equipment Installation